Question: Microsoft Project Essential Training 6. When you want to delay tasks, you add _____ duration values in the _____ field. Select an answer: elapsed; Delay
Microsoft Project Essential Training
6. When you want to delay tasks, you add _____ duration values in the _____ field.
Select an answer:
-
elapsed; Delay
-
elapsed; Leveling Delay
-
regular; Delay
-
regular; Leveling Delay
7. A resource is overallocated by two simultaneous assignments. One of the tasks is very short, while the other task is long. Which technique provides an easy solution to this situation?
Select an answer:
-
assigning a resource with available time to the short task
-
assigning multiple resources to both tasks
-
delaying the long task to finish after the short one is complete
-
splitting the long task
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
