Question: Most likely Activity Optimistic 5 Pessimistic 15 7 B 14 21 22 21 33 45 D 16 30 E 18 19 26 F 7 9

Most likely Activity Optimistic 5 Pessimistic 15

Most likely Activity Optimistic 5 Pessimistic 15 7 B 14 21 22 21 33 45 D 16 30 E 18 19 26 F 7 9 10 G 7 9 17 H 8 8 8 4 5 Find the probability of completing the project in 47 days