Question: n Predecessor Duration A _ 9 B A 6 C A 3 D B 8 E C 3 F C 3 G E 5 H
| n | Predecessor | Duration |
| A | _ | 9 |
| B | A | 6 |
| C | A | 3 |
| D | B | 8 |
| E | C | 3 |
| F | C | 3 |
| G | E | 5 |
| H | E,F | 4 |
| I | D,G,H | 11 |
- Draw the network diagram on paper.
- Calculate the ES, EF, LS, LF, and Total Slack (SL)
- Show your work on your diagram (later you will be asked to upload the work on Moodle).
- Answer the question below: what is the total completion time of the project?
- Which activities are on the critical path?