Question: n Predecessor Duration A _ 9 B A 6 C A 3 D B 8 E C 3 F C 3 G E 5 H

n Predecessor Duration
A _ 9
B A 6
C A 3
D B 8
E C 3
F C 3
G E 5
H E,F 4
I D,G,H 11

  1. Draw the network diagram on paper.
  2. Calculate the ES, EF, LS, LF, and Total Slack (SL)
  3. Show your work on your diagram (later you will be asked to upload the work on Moodle).
  4. Answer the question below: what is the total completion time of the project?
  5. Which activities are on the critical path?