Question: NEC 4 Engineering and Construction Contract main Option E . The Project Manager certifies Completion on 0 1 May. The defects date is 5 2
NEC Engineering and Construction Contract main Option E The Project Manager certifies Completion on May. The defects date is weeks after Completion of the whole of the works. The defect correction period is weeks.
QUESTION
Which TWO of the following statements are correct?
Select TWO options.
The Contractor is required to submit its quality plan to the Project Manager for acceptance at the intervals stated in the Contract Data.
The Contractor's quality management system must be approved by the Client before the Contractor is allowed to commence work on Site.
An instruction given by the Project Manager to the Contractor to correct a failure to comply with its quality plan is not a compensation event.
If the Contractor makes a change to its quality plan it should submit the revised plan to the Supervisor for acceptance.
The Project Manager may certify Completion if a notified Defect has not been corrected by the Contractor.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
