Question: need help with 2.11 (b) Earnest time to complete the project (c) Slack on activities E, F. and H 2.11 Given the activities data in

need help with 2.11 (b) Earnest time to complete need help with 2.11
(b) Earnest time to complete the project (c) Slack on activities E, F. and H 2.11 Given the activities data in the table below: OOOWLOI Activity Times (weeks) Preceding activities 3 B 6 8 7 5 10 4 H 5 D. EF 6 G II IUDOU (a) Draw the network (b) Find the critical path. (c) Find the slacks on al activities 2.12 Activity Duration Preceding activities 1 1 2 2 3 3 4 4 3 5 3 2.4 6 8 3 7 2 2.4 8 4 1.5 9 2 17 10 6 2.4 11 5 6. 10 12 10 7.8.11 13 11 7.8.11 14 1 6, 10 15 9 12 16 6. 10 17 12 1R 6 13 14 15