Question: need newtork diagram and solution For the data given below, calculate the optimum project duration and its associated cost. Activities B and C are preceded

need newtork diagram and solution
need newtork diagram and solution For the data
For the data given below, calculate the optimum project duration and its associated cost. Activities B and C are preceded by A, B precedes D and C precedes E. F is preceded by both D and E. Activity Normal Normal Crash Time Cost Cost A 1 100 0 B 3 150 100 C 4 200 50 D 3 200 60 E 4 200 70 F 150 90 * 3 Maximum Crash Time 0 2 1 1 2 1