Question: Question 3 (25 marks) Consider the following data for a project never before attempted by your company: Activity A Expected Time (weeks) 5 Immediate Predecessor(s)

Question 3 (25 marks) Consider the following data for a project never before attempted by your company: Activity A Expected Time (weeks) 5 Immediate Predecessor(s) B 2 U 3 A D 5 B E CD F 7 D a. Draw the network diagram for this project. b. Identify the critical path and estimate the project's duration C. Calculate the slack for each activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
