Question: Net Present Value A project has estimated annual net cash flows of $11,250 for five years and is estimated to cost $46,950. Assume a minimum
Net Present Value
A project has estimated annual net cash flows of $11,250 for five years and is estimated to cost $46,950. Assume a minimum acceptable rate of return of 15%. Use the Present Value of an Annuity of $1 at Compound Interest table below.
| Present Value of an Annuity of $1 at Compound Interest | |||||
| Year | 6% | 10% | 12% | 15% | 20% |
| 1 | 0.943 | 0.909 | 0.893 | 0.870 | 0.833 |
| 2 | 1.833 | 1.736 | 1.690 | 1.626 | 1.528 |
| 3 | 2.673 | 2.487 | 2.402 | 2.283 | 2.106 |
| 4 | 3.465 | 3.170 | 3.037 | 2.855 | 2.589 |
| 5 | 4.212 | 3.791 | 3.605 | 3.352 | 2.991 |
| 6 | 4.917 | 4.355 | 4.111 | 3.784 | 3.326 |
| 7 | 5.582 | 4.868 | 4.564 | 4.160 | 3.605 |
| 8 | 6.210 | 5.335 | 4.968 | 4.487 | 3.837 |
| 9 | 6.802 | 5.759 | 5.328 | 4.772 | 4.031 |
| 10 | 7.360 | 6.145 | 5.650 | 5.019 | 4.192 |
Determine (1) the net present value of the project (if required, round to the nearest dollar) and (2) the present value index (rounded to two decimal places). If required, use the minus sign to indicate a negative net present value.
| (1) Net present value of the project | $ |
| (2) Present value index |
Step by Step Solution