Question: onsider the project described in the table below: Activity Duration Immediate Predecessor M 4 - N 6 M O 5 M P 7 N ,

onsider the project described in the table below:
Activity Duration Immediate Predecessor
M 4-
N 6 M
O 5 M
P 7 N, O
Q 3 O
R 2 P, Q
What is the critical path and the total project duration for the process?
Group of answer choices
M-O-Q-R, Project Duration: 14 days
M-N-O-P-R, Project Duration: 24 days
M-O-P-R, Project Duration: 18 days
M-N-P-R, Project Duration: 19 days