Question: Given the project described in the table below: Activity Duration Immediate Predecessor G 6 - H 8 G I 5 G J 4 H K

Given the project described in the table below:
Activity Duration Immediate Predecessor
G 6-
H 8 G
I 5 G
J 4 H
K 6 H, I
L 2 J, K
What are the Earliest Start Times (EST) and Early Completion Times (ECT) for activity K?
EST =14 days, ECT =20 days
EST =11 days, ECT =17 days
EST =15 days, ECT =21 days
EST =12 days, ECT =18 days