Question: operations management. please help as it is multiple parts and i am lost. rlly need clear answer Use the information below to answer the 24

operations management. please help as it is multiple parts and i am lost. rlly need clear answer
operations management. please help as it is multiple parts and i am
lost. rlly need clear answer Use the information below to answer the
24 master production schedule problems that follow. A firm is planning their
master production schedule for January and February. The forecast for all of
January is 160 and the forecast for all of February is 200.
Assume. four weeks in each month. There are firm customer orders for
the first five weeks. They are: 50,42,18,6, and 2. The production lot
size is 100 and beginning inventory is 75 . Develop the MPS
and calculate projected inventory and available to promise. Use those calculations to
answer the following questions. Question 30 (1 point) What is the master
production schedule for period 1? If no production is scheduled, enter a
zero. Your Answer: Answer What is the master production schedule for period
2 ? If no production is scheduled, enter a zero. Your Answer:
Answer Question 32 (1 point) What is the master production schedule for

Use the information below to answer the 24 master production schedule problems that follow. A firm is planning their master production schedule for January and February. The forecast for all of January is 160 and the forecast for all of February is 200. Assume. four weeks in each month. There are firm customer orders for the first five weeks. They are: 50,42,18,6, and 2. The production lot size is 100 and beginning inventory is 75 . Develop the MPS and calculate projected inventory and available to promise. Use those calculations to answer the following questions. Question 30 (1 point) What is the master production schedule for period 1? If no production is scheduled, enter a zero. Your Answer: Answer What is the master production schedule for period 2 ? If no production is scheduled, enter a zero. Your Answer: Answer Question 32 (1 point) What is the master production schedule for period 3 ? If no production is scheduled, enter a zero. Your Answer: Answer What is the master production schedule for period 4 ? If no production is scheduled, enter a zero. Your Answer: Answer Question 34 (1 point) What is the master production schedule for period 5 ? If no production is scheduled, enter a zero. Your Answer: Answer What is the master production schedule for period 8 ? If no production is scheduled, enter a zero. Your Answer: Answer Question 38 (1 point) What is the projected inventory for period 1 ? Enter a zero if there is no inventory. Your Answer: Answer What is the projected inventory for period 2? Enter a zero if there is no inventory. Your Answer: Answer Question 40 (1 point) What is the projected inventory for period 3 ? Enter a zero if there is no inventory. Your Answer: Answer What is the projected inventory for period 4 ? Enter a zero if there is no inventory. Your Answer: Answer Question 42 (1 point) What is the projected inventory for period 5 ? Enter a zero if there is no inventory. Your Answer: Answer What is the projected inventory for period 6 ? Enter a zero if there is no inventory. Your Answer: Answer Question 44 (1 point) What is the projected inventory for period 7? Enter a zero if there is no inventory. Your Answer: Answer What is the projected inventory for period 8 ? Enter a zero if there is no inventory. Your Answer: Answer Question 46 ( 1 point) What is the available to promise for period 1? If available to promise is not calculate for that period, enter a zero. Your Answer: Answer What is the available to promise for period 2 ? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer Question 48 (1 point) What is the available to promise for period 3 ? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer What is the available to promise for period 4 ? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer Question 50 (1 point) What is the available to promise for period 5? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer What is the available to promise for period 6 ? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer Question 52 (1 point) What is the available to promise for period 7? If available to promise is not calculated for that period, enter a zero. Your Answer: Answer What is the available to promise for period 8 ? If available to promise is not calculated for that period, enter a zero. Your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!