Question: Part 3 Remember the old saying, A project plan is not a schedule until resources are committed. This exercise illustrates this subtle, but very important,

Part 3
Remember the old saying, A project plan is not a schedule until resources are committed.
This exercise illustrates this subtle, but very important, difference.
Part A
Using your files from Part 2 input resources and their costs if you have not already
done so. All information is found in Tables A2.10 and A2.11.
TABLE A2.10 Conveyor Belt Project; Schedule
Activity Description Resource Duration (days) Preceding Activity
1 Architectural decisions Design 25
2 Hardware specifications Development, design 501
3 Kernel specifications Design 201
4 Utilities specifications Development, design 151
5 Hardware design Design, development 702
6 Disk drivers Assembly, development 1003
7 Memory management Development 903
8 Operating system documentation Design, documentation 253
9 Routine utilities Development 604
10 Complex utilities Development 804
11 Utilities documentation Documentation, design 204
12 Hardware documentation Documentation, design 305
13 Integration first phase Assembly, development 506,7,8,9,10,11,12
14 Prototypes Assembly, development 8013
15 Serial I/O drivers Development 13013
16 System hard/software test Assembly 2514,15
17 Order circuit boards Purchasing 516
18 Network interface Development 9016
19 Shell Development 6016
20 Project documentation Documentation, development 5016
21 Assemble preproduction models Assembly, development 3017F-S, lag 50 days
22 Integrated acceptance testing Assembly, development 6018,19,20,21
Note: F-S refers to a Finish-to-Start lag.
TABLE A2.11
Organization
Resources
Name Group Cost ($/hr)
Design R&D (2 teams) $100
Development R&D (2 teams)70
Documentation R&D (1 team)60
Assembly/test R&D (1 team)70
Purchasing Procurement (1 team)40 Prepare a memo that addresses the following questions:
1. Which if any of the resources are overallocated?
2. Assume that the project is time constrained and try to resolve any overallocation
problems by leveling within slack. What happens?
3. What is the impact of leveling within slack on the sensitivity of the network?
Include a Gantt chart with the schedule table after leveling within slack.
4. Assume the project is resource constrained and resolve any overallocation
problems by leveling outside of slack. What happens? What are the managerial
implications?
5. What options are available at this point in time?
Include a Gantt chart with the schedule table after leveling outside of slack.
Note: No splitting of activities is allowed.
Note: No partial assignments (e.g.,50 percent). All resources must be assigned 100

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!