Question: PLEASE ANSWER ALL!! 11 If an activity whose normal duration is 13 days can be shortened to 11 days for an added cost of $2,500,

PLEASE ANSWER ALL!!PLEASE ANSWER ALL!! 11 If an activity whose

11 If an activity whose normal duration is 13 days can be shortened to 11 days for an added cost of $2,500, what is the crash cost per period? A) $500 B) $1,250 C) $750 D) $13,000 E) $2,500 12) A foundry produces circular utility access hatches (manhole covers). Currently, 220 covers are produced in a 10-hour shift. If labor productivity can be increased by 20%, it would then be: A) 14.4 covers/hr. B) 26.4 covers/hr. C) 264 covers/hr. D) 1200 covers/hr. E) 10 covers/hr