Question: Please assist me with this question Task Description Duration Predecessor (Working Days) A Requirement Analysis 5 B Systems Design 15 A Programming 25 B Telecoms
Please assist me with this question

Task Description Duration Predecessor (Working Days) A Requirement Analysis 5 B Systems Design 15 A Programming 25 B Telecoms 15 B Hardware Installation 30 B Integration 10 C. D G System Testing 10 E. F H Training / Support 5 G - Handover and Go-Live 5 H Question 1 (25 MARKS) 1.1 Determine the critical path of the project. (15 Marks)