Question: please help!!! urgent Given is a CPM project network diagram as shown below a) The Project Completion time = Blank 1 days b) The Earliest
Given is a CPM project network diagram as shown below a) The Project Completion time = Blank 1 days b) The Earliest Start time, ES, of Activity G - Blank 2 days c) The Latest Finish time, LF, of Acitivity C = Blank 3 days. 6) The critical activities ase = Blank 4 (ex Fill in answer as ABCD)