Question: Please show every working 7. In the network diagram presented below, numbers on each arrow refer to the expected time and standard deviation in weeks

Please show every working
7. In the network diagram presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks. 9,2 4.1 8.2 6.0 14.4 1.0 10,3 Determine each of the following: a. the activities which are on the critical path b. the expected project duration c. the probability that the project will be completed in 29 weeks or lessStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
