Question: PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate
PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 18 | - |
| B | 9 | - |
| C | 18 | A |
| D | 7 | B |
| E | 6 | D |
| F | 14 | A,E |
| G | 2 | F |
| H | 7 | C,G |
What is the duration of the project? weeks What is the lateststart week for activity A? What is the slack timefor activityD? weeks If activity D were shortened by 4weeks, what would be the newduration of the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
