Question: PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate
PM.53Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | 22 | - |
| B | 9 | - |
| C | 14 | A |
| D | 6 | B |
| E | 4 | D |
| F | 9 | A,E |
| G | 3 | F |
| H | 7 | C,G |
What is the duration of the project? weeks What is the lateststart week for activity A? What is the slack timefor activityF? weeks If activity C were shortened by 3weeks, what would be the newduration of the project? weeks