Question: Problem # 2 Complete this table using the information below for the project AT THE END OF WEEK # 4 . Network Logic: PERCENT -

 Problem #2 Complete this table using the information below for the
Problem #2
Complete this table using the information below for the project AT THE END OF WEEK #4.
Network Logic:
PERCENT-COMPLETION REPORT
\table[[Activity,Date Started,% Completed,\table[[Time to],[Complete]]],[AB,21,100%,-],[AC,21,60%,2],[AD,21,100%,-],[DE**,not started,-,3],[BF,214,40%,3],[PERCENT-COMPLETION REPORT],[Activity,Date Started,% Completed,\table[[Time to],[Complete]]],[AB,21,100%,-],[AC,21,60%,2],[AD,21,100%,-],[DE**,not started,-,3],[BF,214,40%,3]]
PROJECT PLANNING BUDGET: WEEKS AFTER GO-AHEAD
\table[[Activity,1,2,3,4,5,6,7,8],[AB,2,000,2,000,2,000,-,-,,,-],[AC,3,000,4,000,4,000,4,000,5,000,-,-,-],[AD,2,000,3,000,2,500,-,-,,-,-],[BF,-,-,-,2,000,3,000,4,000,3,000,3,000],[CE,-,-,-,-,-,2,500,-,-],[DE,-,-,-,3,500,3,500,3,500,-,],[EF,-,-,-,-,-,-,3,000?,],[Total,7,000,9,000,8,500,9,500,11,500,10,000,6,000,3,000]]
COST SUMMARY
\table[[Activity,Week Ending,Cumulative to Date],[\table[[Budget],[Cost]],Actual,\table[[(Over)],[Under]],\table[[Budget],[Cost]],Actual],[AB,-,-,-,6,000,6,200],[AC,4,000,4,500,(500),15,000,12,500],[AD,-,2,400,(2,400),7.500,7.400],[BF,2,000,2,800,(800),2,000,4,500],[DE,3,500,-,3,500,3,500,-],[Total,9,500,9,700,(200),34,000,30,600]]
project AT THE END OF WEEK #4. Network Logic: PERCENT-COMPLETION REPORT \table[[Activity,Date

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!