Question: Problem 4 You are managing a task on the critical path which hasa 1 4 6 of $ 5 0 0 , 0 0 0
Problem
You are managing a task on the critical path which hasa of $ The task is percent complete. The team has completed wreets on the tealk and it was scheduled to take weeks. You have spent $ on the task so far. Calentate the cest performance index CP and schedule performance index SP Bricly cxplain what the recults mean.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
