Question: Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time TIME ESTIMATES ( DAYS )

Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time
TIME ESTIMATES(DAYS)
Activity a m b
15817
271013
3357
4135
5468
6333
7345
 Given the following network and activity time estimates, determine earliest and