Question: Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the expected project completion time and variance, and the

Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.

TIME ESTIMATES (DAYS)

ACTIVITY

ACTIVITY PREDECESSOR

a

m

b

A

-

5

 8

17

B

-

7

10

13

C

A

3

 5

 7

D

A

1

 3

 5

E

B, C

4

 6

 8

F

B, C

3

 3

 3

G

D,E

3

 4

 5

Step by Step Solution

3.55 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity ACTIVITY before Optimistic a Most likely M Pessimistic b PERT Estimate a4Mb6 Dev... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!