Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the
Fantastic news! We've Found the answer you've been seeking!
Question:
Given the following network and activity time estimates, determine the earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.
TIME ESTIMATES (DAYS) | |||||||
ACTIVITY | ACTIVITY PREDECESSOR | a | m | b | |||
A | - | 5 | 8 | 17 | |||
B | - | 7 | 10 | 13 | |||
C | A | 3 | 5 | 7 | |||
D | A | 1 | 3 | 5 | |||
E | B, C | 4 | 6 | 8 | |||
F | B, C | 3 | 3 | 3 | |||
G | D,E | 3 | 4 | 5 |
Related Book For
Posted Date: