Question: Product A is assembled from one B and two C s . Each item requires one or more operations, as shown below. The MPS is
Product is assembled from one and two Each item requires one or more operations, as shown below.
The MPS is given below:
tablePeriodProduct A
The routing and work standard file:
tableOperationItem,Work Centre,tableStandard time perunit hrCMachining,CHeat treat,BMachining,AAssembly,
a Complete the requirement matrix and load profile chart for each work center.
Requirements Matrix
tableItem