Question: Project A Questions 3 8 through 4 4 below refer to Project A . To help you correctly answer these questions, you can calculate the
Project A
Questions through below refer to Project A To help you correctly answer these questions, you can calculate the Early Start ES time, Early Finish EF time, Late Start LS time, and Late Finish LF time for all activities and fill them in the network diagram of project A Note that time is given in weeks.
What is the critical path?
What is the total duration of the critical path?
If activity E is delayed by weeks all other activities keep same as the original number it will change the time required to complete the project
If activity B is delayed by week all other activities keep same as the original number it will chnage the time required to complete the project
If activity F is delayed by weeks all other activitues keep the same as the original number the critical path will stay the same
If activity I is completed weeks all other acitivites keep the same as the original number early it will change the time required to complete the project
If activity B took weeks to complete all other activities keep same as the original number what will the new critical path be
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
