Question: Project A Questions 3 8 through 4 4 below refer to Project A . To help you correctly answer these questions, you can calculate the

Project A
Questions 38 through 44 below refer to Project A. To help you correctly answer these questions, you can calculate the Early Start (ES) time, Early Finish (EF) time, Late Start (LS) time, and Late Finish (LF) time for all activities and fill them in the network diagram of project A. Note that time is given in weeks.
1. What is the critical path?
2. What is the total duration of the critical path?
3. If activity E is delayed by 3 weeks (all other activities keep same as the original number) it will change the time required to complete the project
4. If activity B is delayed by 1 week (all other activities keep same as the original number) it will chnage the time required to complete the project
5. If activity F is delayed by 4 weeks (all other activitues keep the same as the original number) the critical path will stay the same
6. If activity I is completed 4 weeks (all other acitivites keep the same as the original number) early it will change the time required to complete the project
7. If activity B took 7 weeks to complete (all other activities keep same as the original number) what will the new critical path be
 Project A Questions 38 through 44 below refer to Project A.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!