Question: Project B: If there is a work delay with Activity A , and it now takes 5 days, what is the new slack for D

Project B: If there is a work delay with Activity A, and it now takes 5 days, what is the new slack for D?
\table[[Activity,Immediate Predecessor,Activity Duration],[A,-,4],[B,-,2],[C,-,6],[D,A,B,2],[E,B,9],[F,D,E,5],[G,C,E,3],[H,G,F,9]]