Question: A project network is given by the following table. Draw the network in your Final Examination Work File and show all path lengths. The minimum
A project network is given by the following table. Draw the network in your Final Examination Work File and show all path lengths. The minimum time required to complete the project is:
Question 1: Show complete work by providing the network, calculating all paths, and by completing the following table.
|
| ES | LS | EF | LF | slack |
| A |
|
|
|
|
|
| B |
|
|
|
|
|
| C |
|
|
|
|
|
| D |
|
|
|
|
|
| E |
|
|
|
|
|
| F |
|
|
|
|
|
| G |
|
|
|
|
|
| Activity | Immediate Predecessors | Activity Time |
| A | - | 5 days |
| B | A | 10 days |
| C | A | 9 days |
| D | B, C | 7 days |
| E | A | 4 days |
| F | D, E | 3 days |
| G | D, F | 3 days |