Question: Project management (2) Consider the following project: Activity Immediate Predecessors A B D E F G Durations (weeks) 5 3 2 3 A B ,

Project management (2) Consider the following
Project management (2) Consider the following project: Activity Immediate Predecessors A B D E F G Durations (weeks) 5 3 2 3 A B , D.E 7 3 6 2 Which activity is not a critical activity? F OO Type here to search o RI e E Esc F2 F3 F4 F5 F6 F7 F8 a