Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C%media:cm.png% D

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C%media:cm.png% D 4 F D 3 G F 1 H E%media:cm.png% G 2