Question: Project X has the data points below. Which task is behind schedule AND under budget?TaskBCWSBCWPACWP 1 , 0 0 0 1 , 1 0 0
Project X has the data points below. Which task is behind schedule AND under budget?TaskBCWSBCWPACWPQRSO Task SO Task QO Task P Task R