Question: Project X Schedule Project X Schedule Task Predecessor Duration (weeks) E(T) A 2 B A 1 C 7 D B 3 E B, C 4

Project X Schedule Project X Schedule Task

Project X Schedule Project X Schedule Task Predecessor Duration (weeks) E(T) A 2 B A 1 C 7 D B 3 E B, C 4 F E 5 G D, F 1 (a) Use the information in the table above to draw a PERT Chart / Network Diagram, including on each node the task name, the task duration, the ES, EF, LS, and LF times. [9 marks] (b) Use the information in the table above to draw a GANTT chart for the project. [6 marks] (c) Find the critical path of the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!