Question: Q11: The critical path for the network activities shown below is _____ with duration ______. Activity Du ration Immediate A 2 --- B 4 ---

Q11:

The critical path for the network activities shown below is _____ with duration ______. Activity Du ration Immediate A 2 --- B 4 --- C 6 A,B D 1 A,B E 2 B,C,D

a.

A-C-E; 10

b.

None of the choices are correct

c.

B-E; 6

d.

B-D-E; 7

e.

A-C-E; 12