Question: 13. The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 B 1 A C
13.
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | |
| B | 1 | A |
| C | 7 | |
| D | 1 | A |
| E | 3 | B, C, D |
- A.
A-B-C-D-E; 16
- B.
B-C-D; 9
- C.
A-B-E; 8
- D.
C-E; 10
- E.
A-D-E; 8
14.
A contractor's project being analyzed by PERT has an estimated time for the critical path of 133 days. The sum of all activity variances is 57; the sum of variances along the critical path is 47. The probability that the project will take 151 or more days to complete is
- A. 0.004
- B. 0.996
- C. 0.649
- D. 0.009
- E. 0.351