Question: Q2. From the table shown i) Shown the network diagram and calculate the critical path (Points 6) Project duration (Point 1) Float of task C

Q2. From the table shown i) Shown the network

Q2. From the table shown i) Shown the network diagram and calculate the critical path (Points 6) Project duration (Point 1) Float of task C (Point 1) iv) Early Start of task E (Point 1) v) Late Finish of Task A (Point 1) Activity Predecessor Duration A 0 5 B 0 6 . 2 D A,B 5 E B 4 F C, D, E 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!