Question: Question 1 4 2 0 p t s A precedence schedule of a project is given below. Compress the schedule in accordance with the data
Question
A precedence schedule of a project is given below. Compress the schedule in accordance with the data given in the following table. The total direct cost of each activity is given in the table for normal and crash situations and the indirect overhead cost as $ per day.
tableActivityDuration DaysCost $NormalCrash,Normal,CrashABCDEFGH
What is the Leastcost duration?
What is the crash duration?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
