Question: Question 1 4 2 0 p t s A precedence schedule of a project is given below. Compress the schedule in accordance with the data

Question 14
20pts
A precedence schedule of a project is given below. Compress the schedule in accordance with the data given in the following table. The total direct cost of each activity is given in the table for normal and crash situations and the indirect (overhead) cost as $100 per day.
\table[[Activity,Duration (Days),Cost ($)],[Normal,Crash,Normal,Crash],[A,3,2,1500,1800],[B,2,1,800,900],[C,7,4,2800,3100],[D,5,4,1000,1150],[E,4,3,800,850],[F,6,4,600,700],[G,3,3,1500,1500],[H,5,5,1000,1000]]
-What is the Least-cost duration?
-What is the crash duration?
 Question 14 20pts A precedence schedule of a project is given

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!