Question: Question 1 . [Project Quality Management, Statistical Process Control Charts] In a project, Length has been identified as a quality characteristic to be monitored by
Question 1. [Project Quality Management, Statistical Process Control Charts]
In a project, "Length" has been identified as a quality characteristic to be monitored by a process control chart. The quality characteristic is assumed to be Normally distributed. The following measurements from an experiment under control were obtained.
| Item # | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Length in Millimeters | 321 | 305 | 317 | 302 | 302 | 304 | 318 | 308 | 315 | 316 | 320 | 316 |
Using the data, construct a simple process control chart. What is the "lower control limit", the "center line", and the "upper control limit" of the control chart? (Use Population Variance)
| Chart | A | B | C | D | E |
| UCL (Upper Control Limit) | 319 | 318 | 314 | 333 | None of the above |
| CL (Center Line) | 312 | 312 | 312 | 312 | |
| LCL (Lower Control Limit) | 305 | 306 | 310 | 291 |