Question: Task C has two immediate predecessors, Tasks A and B. Task C atso has two immedate followers, Tasks D and E. Task A has an

Task C has two immediate predecessors, Tasks A
Task C has two immediate predecessors, Tasks A and B. Task C atso has two immedate followers, Tasks D and E. Task A has an eary finith time of 3 Gajs, and Task 8 has an early finish time of 5 days. Task D has a late start time of 10 days and Task E has a late atart time of 8 days. Task C is 2 tape iony 3 day What is the early finish time of Task C? 5 days 7 days 2 days 6 days 8 days