Question: Question 14 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistid Activity Predecessor Time

Question 14 (1 point) The following represents a

Question 14 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistid Activity Predecessor Time Time Time A 2 8 14 B - 8 8 8 A 6 9 18 D B N 11 17 What is the minimum expected completion time for the project (please round off to two decimal digits)? Your Answer: Your