Question: Question 2 2 0 p t s The critical path for the network activities shown below is with duration table [ [ Activity ,

Question 2
20pts
The critical path for the network activities shown below is with duration
\table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,4,],[B,6,A. A],[C,7,-],[D,4,A],[E,5,B.C,D]]
C-E: 12
A-B-E; 11
A-B-C-D-E: 22
A-D-E: 13
A-B-E;15