Question: Question 2 4 points Set (CH) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what

Question 2 4 points Set (CH) A project was
Question 2 4 points Set (CH) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what would be the cost Variance given the following earned he analysis in AED EV - AED 650.000: PV - AED 750.000 AC = AED ROO,000. a. 150.000 b. +150.000 c. 50.000 d. 50,000 eston 2 of 30