Question: Question 27 ICH 7) A project was estimated to cost AED 1.5M and scheduled to last for months. After three months, what would be the

Question 27 ICH 7) A project was estimated to
Question 27 ICH 7) A project was estimated to cost AED 1.5M and scheduled to last for months. After three months, what would be the schedule Vance the following and value analysis in AED? EV - AED 650.000 PV - AED 750.000: AC - AED 300.000 3.100.000 b. +100,000 oc-50,000 d. +50,000 Moving to another question will save this response Question of 30