Question: Question 2: (5 point) Schedule the following activities using CPM: Task Time Preceding Task (Weeks) Tasks A 1 B 4 A C 3 A D

Question 2: (5 point) Schedule the following

Question 2: (5 point) Schedule the following activities using CPM: Task Time Preceding Task (Weeks) Tasks A 1 B 4 A C 3 A D 2B E 5 C, D F 2D G 2 F H 3 E,G G Part (a) Draw the network (2 points): Part (b) What is the critical path? (1 point) Part (c) How many weeks will it take to complete the project? (1 point) Part (d) What activities have slack, and how much? (1 point)