Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 4 C A 6 D B 1 E

Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 6
D B 1
E C D 4
F D 3
G F 1
H E G 2
b. What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-C-E-H
A-B-D-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
BPicture 5 weeksPicture CPicture 2 weeksPicture FPicture 3 weeksPicture HPicture 2 weeks.
BPicture 1 weekPicture CPicture 2 weeksPicture EPicture 3 weeksPicture HPicture 4 weeks.
BPicture 1 weekPicture DPicture 1 weekPicture FPicture 1 weekPicture GPicture 1 week.
PrevQuestion 4 of 5 Total4 of 5Visit question mapNext

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!