Question: A task has an optimistic completion time of 4 days, a most likely time of 10 days, and a pessimistic time of 13 days. The

A task has an optimistic completion time of 4 days, a most likely time of 10 days, and a pessimistic time of 13 days. The expected task duration is:

A.

11.5 days

B.

10 days

C.

11 days

D.

10.5 days

E.

9.5 days

F.

12 days