Question: Question 2 Based on case study above, assuming that your project team will work a standard working week (5 working days in 1 week) and

Question 2 Based on case study above, assuming that your project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible. Activity A B D E F G H 1 Description Requirement Analysis System Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover/Go-Live Predecessor(s) Duration (days) 5 A 15 B 25 B 15 B 30 C,D 10 E, F 10 G 5 5 Develop an activity-on-node network diagram and state important times for each activity as follows: i. Early start date (ES) ii. Early finish date (EF) Late start date (LS) iv. Late finish date (LF) Expected completion time for the project. (25 Marks) V