Question: Question 2. Calculate ES, EF, LS, LF, TF, & FF for all activities and fill out the table below: 6 2 3 B SF 4

Question 2. Calculate ES, EF, LS, LF, TF, & FF

Question 2. Calculate ES, EF, LS, LF, TF, & FF for all activities and fill out the table below: 6 2 3 B SF 4 D -FF 2- F FS 2 FS 1 2 SS 2 H 2 3 4 5 FS-1 SS 1 -FS-1 E -FF 1 ES EF LS LF TF FF A B C D E F G H a. What is the total duration of the project? b. Identify critical path(s)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!