Question: Question 2. If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14

Question 2. If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11 weeks, and $1, 150 for 10 weeks, what is the optimum cost-time schedule for the project? What is the cost? Activity Crash Cost Maximum Crash Normal Time Normal Cost (slope Time 0 0 W D 150 100 2 200 50 1 D 250 40 1 W N A W A E 200 0 0 F 250 30 2 200 20 1 250 60 N A N - N 300 200 200 B F G 3 2 A D 3 4 2 C E H 3 2