Question: Question 2 options: Pic TIMES ( days ) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1 2 2 3

Question 2 options:
Pic
TIMES (days)
Activity
Start Node
Finish Node
OPTIMISTIC
to
MOST LIKELY
tm
PESSIMISTIC
tp
A
1
2
23
32
59
B
1
3
15
18
27
C
2
5
19
31
67
D
3
4
28
46
64
E
4
5
15
42
69
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values:
Activity A.........te =35
Standard Deviation =6
Activity B.........te =
Standard Deviation =
Activity C.........te =
Standard Deviation =
Activity D.........te =
Standard Deviation =
Activity E.........te =
Standard Deviation =9
Path 125
Mean Time =
Standard Deviation =10
Path 1345
Mean Time =
Standard Deviation =
 Question 2 options: Pic TIMES (days) Activity Start Node Finish Node

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!