Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 34 61 B 1

TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

25

34

61

B

1

3

21

27

39

C

2

5

18

42

66

D

3

4

32

50

68

E

4

5

8

20

44

Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 37 Standard Deviation = 6 Activity Bte =

Standard Deviation =

Activity Cte =

Standard Deviation =

Activity Dte =

Standard Deviation =

Activity Ete =

Standard Deviation = 6 Path 1 2 5 Mean Time =

Standard Deviation =10

Path 1 3 4 5 Mean Time =

Standard Deviation =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!