Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 34 61 B 1

|
|
|
| TIMES (days) |
| |
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 25 | 34 | 61 |
| B | 1 | 3 | 21 | 27 | 39 |
| C | 2 | 5 | 18 | 42 | 66 |
| D | 3 | 4 | 32 | 50 | 68 |
| E | 4 | 5 | 8 | 20 | 44 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 37 Standard Deviation = 6
Activity Bte = Standard Deviation =
Activity Cte = Standard Deviation =
Activity Dte = Standard Deviation =
Activity Ete = Standard Deviation = 6 Path 1 2 5 Mean Time = Standard Deviation =10 Path 1 3 4 5 Mean Time = Standard Deviation =