Question: Question 4 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 23 32

Question 4 options:

TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

23

32

59

B

1

3

22

28

40

C

2

5

12

24

60

D

3

4

30

39

66

E

4

5

15

33

51

Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 35 Standard Deviation = 6

Activity Bte = Standard Deviation =

Activity Cte = Standard Deviation =

Activity Dte = Standard Deviation =

Activity Ete = Standard Deviation = 6 Path 1 2 5 Mean Time = Standard Deviation =10 Path 1 3 4 5 Mean Time = Standard Deviation =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!